On January 19, 2026, the Pala Sub Court dismissed a civil suit in which the Kerala government claimed ownership of 2,263 acres of Cheruvally Estate.

Ownership dispute and airport proposal

The ruling favoured the ownership claim of Ayana Charitable Trust, which is associated with the Believers Eastern Church. Cheruvally Estate had been identified as the proposed site for the Sabarimala Greenfield Airport. The court’s order addressed the ownership dispute, not the airport proposal. The Kerala government was considering an appeal.

Important Facts for Exams

  • Proposed footprint: The proposed airport is planned over 870 acres, with its site spread across Erumely and Manimala.
  • Runway design: The proposed airport's infrastructure plan specifies a single runway measuring 3,500 metres and designated 08/26.
  • Environmental assessment: Louis Berger completed the feasibility report in December 2018, but did not conduct an environmental impact assessment because land acquisition lacked a final decision.