Pallivasal Extension Adds 60 MW to Kerala Grid
Kerala Chief Minister Pinarayi Vijayan inaugurated the 60-MW Pallivasal Extension Scheme in Idukki in March 2026. Its two 30-MW generators add capacity to the State’s power grid. The project, implemented by the Kerala State Electricity Board (KSEB), extends the Pallivasal Hydroelectric Project, commissioned in 1940.
Project timeline and revised cost
First sanctioned in 2001 at ₹175.86 crore, the scheme received a formal revised administrative sanction of ₹632.59 crore through a KSEB order dated 24 November 2026. The work was awarded to the ESSAR-DEC-CPPL Consortium in 2006 for ₹268.01 crore, with completion scheduled for 1 March 2011. After technical and contractual difficulties, KSEB terminated the contract in 2018 and completed the remaining work in separate packages. The board had issued individual sanctions for these works rather than one consolidated revised sanction.
Review of project delays
In October 2026, KSEB directors decided to commission an independent study by an external expert agency or committee to recommend improvements to project management. In February 2026, KSEB accepted its Vigilance wing’s report and decided against action on officials. The inquiry found lapses that contributed to delay but no evidence of malicious or wilful intent, or vested interest.
Important Facts for Exams
- Hydraulic layout: Pallivasal Hydroelectric Project comprises two reservoirs, two dams, a diversion dam and a powerhouse, linking water storage and generation infrastructure.
- Development phases: Pallivasal’s first phase achieved 15 MW with three 5-MW units; a second phase added three 7.5-MW turbines and two water-storage dams.
- Utility structure: KSEB operates as a vertically integrated state utility, combining electricity generation, transmission and distribution rather than separating these functions among successor companies.
- Small-hydro threshold: In India, hydropower projects with installed capacity up to 25 MW are classified as small hydro and fall under the Ministry of New and Renewable Energy.