NGT Orders Monitoring and Action Around Kerwa Dam

NGT Orders Monitoring and Action Around Kerwa Dam

On 6 February 2026, the National Green Tribunal’s Central Regional Bench in Bhopal directed authorities to monitor the area around Kerwa Dam and remove encroachments. The action followed reports of environmental violations in the Kaliyasot-Kerwa Dam area, raised initially by green activist Rashid Noor Khan.

Findings and tribunal directions

A joint committee comprising officials from the district administration, Water Resources Department, Madhya Pradesh Pollution Control Board and State Wetland Authority confirmed illegal filling of up to 10 feet within the dam’s Full Tank Level boundary at Mahuakheda village. The material included kopra, murrum and black soil. The tribunal said the activity threatened water storage, structural safety and ecology, violated the Wetland (Conservation and Management) Rules 2017 and other environmental laws, and could not be justified by private land ownership.

Monitoring and protection measures

The State Wetland Authority must identify and demarcate a Zone of Influence around Kerwa and Kaliyasot dams within two months. The Collector, Divisional Forest Officer and Chief Executive Officer of Bhopal were directed to remove encroachments within their jurisdictions. The Principal Secretary of the Water Resources Department must form patrolling teams to check Full Tank Level boundaries at least twice a month. The tribunal also stated that a clean environment is a fundamental right under Article 21. Kerwa Dam supplies an alternative drinking-water source for Bhopal and irrigation for thousands of hectares.

Important Facts for Exams

  • Procedural rules: The National Green Tribunal follows natural-justice principles rather than strict Code of Civil Procedure procedure and is not bound by the Indian Evidence Act.
  • Decision principles: When making orders, the National Green Tribunal applies sustainable development, the precautionary principle and the polluter-pays principle.
  • Supreme Court appeal: After an unsuccessful tribunal review, an order may be challenged before the Supreme Court within ninety days.
Originally written on February 6, 2026 and last modified on November 19, 2026.