Karnataka High Court Upholds Quashing of NICE Project Land Acquisition
On July 29, 2026, a Karnataka High Court division bench dismissed appeals by Nandi Infrastructure Corridor Enterprises (NICE) and the Karnataka Industrial Areas Development Board (KIADB), upholding the quashing of land acquisition for the Bengaluru-Mysuru Infrastructure Corridor (BMIC), also known as the NICE Road project.
Court Upholds Earlier Order
Justices D.K. Singh and T.M. Nadaf upheld a single-judge order dated July 4, 2025, which quashed the project’s final land-acquisition notification. The bench called on the state government to conduct an independent investigation and forensic audit into alleged irregularities. The ruling brought relief to hundreds of farmers whose land was acquired.
Court Notes Delayed Compensation
The court noted that compensation awards had not been passed for more than two decades for land acquired between 1998 and 2009. It observed that the BMIC project “may be one of the biggest scams in the State of Karnataka” and said farmers had lost land and livelihoods without compensation.
Important Facts for Exams
- Planned expressway: The Bengaluru–Mysuru Infrastructure Corridor was planned as a privately tolled, four-to-six-lane expressway connecting Bengaluru and Mysuru.
- Project consortium: A 1995 trade mission to India helped launch the corridor project; its development consortium included Kalyani Group, VHB International and SAB International.
- KIADB statutory basis: KIADB is a statutory body constituted under the Karnataka Industrial Areas Development Act, 1966, with powers to develop industrial areas and facilitate land acquisition.
- KIAD Act acquisition stages: Section 28 of the Karnataka Industrial Areas Development Act provides a staged acquisition process: preliminary notification, consideration of objections, final declaration and subsequent possession.