Karnataka High Court Limits KPTCL’s Power to Revise Supervision Fees

Karnataka High Court Limits KPTCL’s Power to Revise Supervision Fees

The Karnataka High Court ruled on June 26, 2026, that the Karnataka Power Transmission Corporation Limited (KPTCL) cannot unilaterally revise supervision charges for customer-managed electricity works without approval from the Karnataka Electricity Regulatory Commission (KERC). Justice Ravi V. Hosmani delivered the ruling on a petition by Anushka Realty Inc.

Court quashes supervision-fee demand

The court quashed KPTCL’s demand for approximately ₹1.2 crore (₹1,20,49,000) from Anushka Realty Inc. It held that the functions assigned to KPTCL under Sections 39 to 41 of the Electricity Act, 2003, do not give it authority to determine or revise charges for self-execution works. The court said KERC alone can frame regulations for such charges under Section 181. Supervision fees must remain within KERC’s prescribed limit: 10% of the estimated work cost or ₹15 lakh, whichever is lower.

Important Facts for Exams

  • Board unbundling: The Electricity Act, 2003 requires states to unbundle State Electricity Boards, but permits them to continue as distribution licensees and state transmission utilities.
  • Network planning: Under the Electricity Act, 2003, central and state transmission utilities are government companies responsible for planned, coordinated development of the transmission network.
  • Transmission-trading separation: A State Transmission Utility must not engage in electricity trading, separating its network-planning and transmission role from competitive power sales.
  • Open-access obligation: Section 40 requires transmission licensees to provide non-discriminatory open access to their systems, subject to statutory conditions and applicable regulations.
Category: Karnataka
Originally written on June 27, 2026 and last modified on November 20, 2026.
Tags: , , , , , , ,

Leave a Reply

Your email address will not be published. Required fields are marked *