CAG Flags Delays in Karnataka’s Yettinahole Project
A Comptroller and Auditor General (CAG) report on the Yettinahole Integrated Drinking Water Project was presented in the Karnataka Legislative Assembly on 29 January 2026. It identified delays, tendering flaws, financial management issues and coordination failures.
Audit findings on implementation
The report noted that ₹15,297 crore had been spent over 12 years, but the project had not yet provided the intended drinking water facilities to Chikkaballapur and Kolar districts. The balancing reservoir’s location was changed twice in the Detailed Project Reports (DPRs), while its planned capacity was reduced from 10 TMC to 2 TMC. Phase 1 infrastructure could not be used because the project phases were not synchronised, leaving the investment unproductive.
Important Facts for Exams
- Water-transfer route: The scheme envisages dams across the Netravati and its tributaries in the Western Ghats, before they join the Arabian Sea.
- Planned transfer volume: Its design envisages pumping about 24 thousand million cubic feet of water to the Western Ghats’ top and the Deccan Plateau.
- Ecological siting: The project’s dams are mostly located in ecologically sensitive parts of Hassan and Dakshina Kannada districts.
Originally written on
January 30, 2026
and last modified on
November 19, 2026.