Uttar Pradesh Cabinet Clears 2,400 MW Meja Expansion
On 18 May 2026, the Uttar Pradesh Cabinet approved three new 800 MW units at the Meja Super Thermal Power Project in Prayagraj, adding 2,400 MW of capacity. The project is estimated to cost ₹38,358 crore.
Meja thermal power expansion
The expansion is planned through a 50:50 joint venture between the Uttar Pradesh government and NTPC. Energy Minister Arvind Kumar Sharma confirmed the approval and said the decision followed a revision of the original plan presented at the 2023 Global Investors Summit.
Mirzapur pooling substation
In a separate decision, the Cabinet approved a 765/400 kV pooling substation with a 4 × 1,500 MVA capacity and associated transmission lines. The project is estimated to cost ₹2,799.47 crore: ₹1,315.91 crore for the substation and bays, and ₹1,483.56 crore for transmission lines.
Important Facts for Exams
- Existing station capacity: Meja Thermal Power Station’s cited planned capacity is 1,320 MW, configured as two 660 MW units.
- Ownership arrangement: Meja Thermal Power Station is owned by MUNPL, a joint venture between NTPC Limited and Uttar Pradesh Rajya Vidyut Utpadan Nigam.