Odisha Sets Timelines for Land Acquisition and Social Impact Assessments
The Odisha government has issued a new Standard Operating Procedure (SOP) to set timelines for land acquisition and Social Impact Assessments (SIA). Issued by the Revenue & Disaster Management Department under Additional Chief Secretary Dr Arabinda Padhee, it covers proposals, public hearings, expert group recommendations and the final declaration under Section 8(2) of the land-acquisition law.
Proposal and assessment deadlines
District Collectors must scrutinise land acquisition proposals and forward them to the State SIA unit within 15 days. The SIA study period is set at 45 to 100 days, depending on the number of landholders involved.
Overall timeline and stated objectives
The process, from proposal submission to the Section 8(2) declaration, is scheduled to take 186 to 286 days. The SOP aims to reduce delays in land acquisition, compensation and rehabilitation, and to improve administrative speed and transparency.
Important Facts for Exams
- Integrated appraisal: Environmental Social Impact Assessment integrates social and environmental appraisal, giving both dimensions equal weight.
- Collector remit: Indian District Collectors handle land acquisition alongside revenue recovery and land reforms, placing acquisition within their wider district revenue responsibilities.
- Expert-group composition: The 2013 land-acquisition law provides for a multidisciplinary expert group including social scientists, local-government representatives, rehabilitation specialists and a technical expert.
- Public-hearing purpose: The law requires a public hearing in the affected area so affected families can express views for recording in the Social Impact Assessment report.