Godavari water began flowing into North Andhra through the Polavaram Left Main Canal on 2 September 2026. The release took place at the canal’s cross-regulator in Payakaraopeta, Anakapalli district. Chief Minister N. Chandrababu Naidu performed Jala Harathi and opened the regulator gates with local farmers.
Canal capacity and planned uses
The 213-km canal has a reported cost of ₹4,192 crore. It is designed to provide irrigation to 2.87 lakh acres across East Godavari, Kakinada, Konaseema and Anakapalli districts. Estimates for its planned drinking-water supply range from 5.23 lakh to 9.23 lakh people. The government also plans to fill 110 tanks in Anakapalli district and replenish the Yeleru canal.
Interim supply and future connection
Water is currently lifted from the Godavari near Purushothapatnam through an interim arrangement because the main Polavaram headworks are not fully operational. Officials clarified that this release does not mean the main Polavaram irrigation project is complete. Future plans envisage connecting the canal to the Uttarandhra Sujala Sravanthi project to carry Godavari water to upland areas of Anakapalli, Visakhapatnam, Vizianagaram, Parvathipuram Manyam and Srikakulam districts.
Important Facts for Exams
- Twin canal capacity: Polavaram’s left and right canals are each designed to carry 17,500 cusecs.
- Monsoon diversion: During July–October, the project can divert nearly 360 tmcft of Godavari flood flows into its canals.