31.5 km of NH-07 Opens to Traffic in Uttarakhand
On 19 January 2026, traffic began operating on 31.5 km of the 44.8-km Paonta Sahib–Dehradun (Ballupur) four-lane NH-07 project, which connects Uttarakhand and Himachal Pradesh.
Project and bypass
The project is being developed at an approximate cost of ₹1,646.21 crore. It includes a 25-km greenfield bypass designed to route traffic around busy settlements, including Paonta Sahib, Herbertpur, Sahaspur, Selaqui and Sudhowala.
Completion target and travel time
The remaining project works were targeted for completion by February 2026. The project is expected to reduce travel time between Dehradun and Paonta Sahib from nearly two hours to approximately 30–35 minutes.
Important Facts for Exams
- Bypass function: A bypass routes through traffic around a built-up area, reducing interference from local traffic and helping ease congestion and improve road safety.
- Greenfield alignment: A greenfield road is built on a new alignment, unlike brownfield widening or rehabilitation, which modifies an existing transport corridor.
- Four-laning standards: The Indian Roads Congress's IRC:SP:84 sets specifications and standards for four-laning highways, including geometric design, pavement, structures and road safety.