Karnataka Cabinet Approves Revised ₹542.96-Crore Hassan Airport Project Cost

Karnataka Cabinet Approves Revised ₹542.96-Crore Hassan Airport Project Cost

The Karnataka Cabinet approved a revised cost of ₹542.96 crore for the Hassan airport project, up from ₹193.65 crore sanctioned in 2021. The additional ₹349.31 crore includes ₹122 crore for land acquisition and ₹227.31 crore for additional works and operating facilities.

The project implementing agency is the Karnataka State Industrial Infrastructure Development Corporation. Work on the ground began in 2021. The airport project has faced delays, including over land acquisition. A minister has said he aims to begin flights within two years; this is a stated target, not a confirmed schedule.

Notable Points

  • Early proposal and site selection: Karnataka first proposed an airport at Hassan in 1967, and the Public Works Department acquired 134.28 acres in 1972. The proposal was revived in 1996. Boovanahalli was selected after surveys assessed physical, environmental, meteorological and economic factors.
  • Earlier project structure: A 2007 proposal envisaged a joint venture between Karnataka and Jupiter Aviation and Logistics Limited, under a build-operate-transfer agreement with a 30-year lease period beginning at commissioning. Plans also included a pilot-training institute and an aircraft-maintenance centre.
  • Earlier land acquisition: An earlier phase required 960 acres. The district administration acquired and handed over 536 acres, while 424 acres remained unacquired; the project did not proceed at that time.
Category: Karnataka