UPERC fines UPPCL ₹7.18 lakh over delayed prepaid-meter reconnections

UPERC fines UPPCL ₹7.18 lakh over delayed prepaid-meter reconnections

On June 3, 2026, the Uttar Pradesh Electricity Regulatory Commission (UPERC) imposed a penalty of ₹7.18 lakh on Uttar Pradesh Power Corporation Limited (UPPCL) for delays in restoring electricity to prepaid smart-meter consumers after recharge.

Penalty and compliance directions

UPERC directed UPPCL to deposit the penalty within 15 days, identify the causes of the delays and take corrective measures.

Reconnection performance standard

The commission reviewed reconnection data from March 13 to April 10, 2026. Contemporaneous reports said performance fell below the prescribed standard on 10 of the 16 days examined. The Standards of Performance Regulations require restoration within two hours of prepaid-meter recharge in at least 95% of cases.

Important Facts for Exams

  • Electricity Act penalty power: Section 142 of the Electricity Act, 2003 empowers the appropriate electricity commission to penalise non-compliance with the Act, regulations or its directions.
  • Consumer compensation for performance failures: Section 57 of the Electricity Act, 2003 requires licensees to meet Commission-set performance standards and makes compensation payable to consumers when those standards are breached.
  • Smart-meter communications: Smart meters support two-way communication, enabling utilities to obtain remote readings and, where configured, perform remote electricity-supply connection or disconnection.
Category: Uttar Pradesh
Originally written on June 6, 2026 and last modified on November 20, 2026.
Tags: , , , ,

Leave a Reply

Your email address will not be published. Required fields are marked *