Fire Damages Equipment at Machhkund Hydropower Station in Odisha, Shuts Six Units, Repairs Expected to Exceed Six Months

Fire Damages Equipment at Machhkund Hydropower Station in Odisha, Shuts Six Units, Repairs Expected to Exceed Six Months

A fire broke out around noon on 23 May 2026 at the Machhkund Hydroelectric Project in Koraput district, Odisha, damaging equipment at the power station. All six generating units, each rated at 120 MW, were shut down safely.

Fire and restoration outlook

The fire reportedly began when a current transformer connected to a 2.5 MVA transformer outside the powerhouse burst. Flames spread through cables into the facility. Employees were evacuated; four reportedly suffered mild suffocation or minor injuries and were treated at Ankadeli Community Health Centre. No fatalities were reported. Firefighters from Lamtaput and Nandapur brought the blaze under control by about 4 p.m. The project is a joint venture of the Odisha and Andhra Pradesh governments. The Andhra Pradesh Power Generation Corporation oversees its operations and administrative control, and is responsible for assessing the damage and losses. Preliminary estimates indicate restoration and resumption of generation could take more than six months.

Important Facts for Exams

  • Instrument-transformer role: A current transformer scales current to standardised values for measuring instruments and protective relays, while isolating their circuits from high voltage.
  • Induction mechanism: A current transformer uses induction: alternating primary current creates a magnetic field in its core, inducing secondary current proportional to the primary current.
  • Open-secondary hazard: A current transformer’s secondary should not be disconnected while primary current flows, because the resulting high voltage can endanger operators.