CAG Polavaram audit tabled in Andhra Pradesh Assembly
The Comptroller and Auditor General of India’s Report No. 4 of 2025 on the Polavaram Irrigation Project was tabled in the Andhra Pradesh Assembly on 6 March 2026. The performance audit covered implementation from 2017–18 to 2022–23 and was conducted between June 2022 and June 2023.
Audit Findings
The audit examined construction, land acquisition, and rehabilitation and resettlement. It found that work on the diaphragm wall and cofferdams proceeded before river diversion through the spillway and spill channel was available. The report said subsequent floodwater damaged the diaphragm wall and cofferdam works. It also flagged tender awards to a single bidder in circumstances that, it said, contravened government rules.
CAG Recommendations
The report recommended following the construction schedule, completing pending diaphragm-wall rectification, and speeding up land acquisition and rehabilitation and resettlement. It also called for a fair and transparent tendering process that promotes competitive bidding.
Important Facts for Exams
- Trench stabilisation: During slurry-wall excavation, liquid slurry applies outward pressure to prevent trench collapse and retards water entering the trench.
- River-work sequencing: Cofferdams are temporary barriers that isolate a construction area from a river; diversion channels or tunnels carry water around the worksite.
- Performance-audit criteria: Performance audits assess economy, efficiency and effectiveness, going beyond checks of financial regularity to examine how well a programme achieves its objectives.
- Single-bid assessment: A single responsive bid does not automatically require retendering; procurement authorities should assess whether publicity and bidding time were adequate and prices reasonable.