Unit II of the Buxar Thermal Power Project achieved commercial operation on 12 September 2026 at Chausa in Buxar district, bihar/">Bihar. The unit has a capacity of 660 MW.

Project details

SJVN Thermal Private Limited, a wholly owned subsidiary of SJVN, implemented the project using supercritical thermal-power technology.

Capacity and power allocation

With both 660 MW units operational, the project’s full installed capacity is 1,320 MW. Under a long-term power-purchase arrangement, 85 percent of its power is allocated to Bihar. Expected annual generation is 9,828.72 million units at an 85 percent plant load factor; this is a projection, not actual annual output.

Important Facts for Exams

  • Project origin: The Buxar Thermal Power Project was conceptualised through a 2013 memorandum of understanding involving SJVN, BSPHCL and BPIC.
  • Supercritical water cycle: Supercritical boilers operate above water’s critical pressure, approximately 22.1 MPa, so water has no distinct liquid-to-vapour boiling transition in the steam circuit.
  • Efficiency and emissions: Improved boiler-cycle efficiency can reduce coal use and carbon dioxide per unit generated, but supercritical conditions alone do not control sulphur dioxide or particulate emissions.