Bihar Cabinet approves five highway projects
The Bihar Cabinet gave administrative approval to five road projects under Bihar State Highway Project IV on 27 May 2026. The approvals cover road widening, strengthening or construction; they do not mean the projects have been completed.
Approved road projects and costs
The Madhubani–Rajnagar–Babubarhi–Khutauna road, about 39 km long, was approved at ₹632.72 crore, while the approximately 51-km Sitamarhi–Pupri–Benipatti road was approved at ₹434.37 crore. The about 48-km Vishunpur–Atarbel–Jale–Ghogharchatti upgrading project on State Highway 97 received approval at about ₹990 crore. Construction of the approximately 47-km Ganpatganj–Parwaha project on State Highway 92 was approved at ₹703.95 crore. The approximately 81-km Brahmpur–Koransarai–Itarhi project and connected Buxar-area roads were approved at ₹982.58 crore.
Important Facts for Exams
- Administrative approval: Administrative approval records a competent authority’s acceptance of a project’s need and estimated expenditure; it is distinct from permission for a contractor to start work.
- Technical sanction: In public-works procedures, technical sanction is a separate engineering check of detailed designs, specifications and estimates, typically preceding tendering.
- State Highway jurisdiction: State Highways fall primarily under state-government responsibility, whereas National Highways are declared under central law and overseen by the Union government.
- Strengthening versus widening: Pavement strengthening increases a road’s structural capacity, often through an overlay; widening adds carriageway width and need not strengthen the existing pavement.