Kilokri, South Delhi
India’s first commercial utility-scale battery energy storage system (BESS) will go live in March 2025. It is located in Kilokri, a village in south Delhi. The BESS is a 20 MW/40 MWh battery cluster that is part of the BSES Rajdhani Power Limited (BRPL) Kilokri substation. The system is expected to provide four hours of power every day, two hours each during the day and at night. The BESS project is a collaboration between BRPL, IndiGrid, and the Global Energy Alliance for People and Planet (GEAPP). The project is a significant milestone in India's efforts to integrate renewable energy and modernize its power infrastructure.