Q. Which among the following is a PPP model?
1. Built-own-operate-transfer
2. Built-operate-Transfer
3. Hybrid-Annuity Model
4. Toll-Operate-Transfer
Choose the correct option from the choices given below:

Answer: 1,2,3 and 4 only
Notes: Under PPP mode the models are:
1. Built-own-operate-transfer
2. Built-operate-Transfer
3. Hybrid-Annuity Model
4. Toll-Operate-Transfer