A work can be completed by P and Q in 12 days, Q and R in 15 days, R and P in 20 days. In how many days P alone can complete the work ?
Q. A work can be completed by P and Q in 12 days, Q and R in 15 days, R and P in 20 days. In how many days P alone can complete the work ?
Answer: 30 days
Notes: (P + Q)'s 1 day's work $latex = \frac{1}{12}&s=1$……….(I) (Q + R)'s 1 day's work $latex = \frac{1}{15}&s=1$…….….(II) (R + P)'s 1 day's work $latex = \frac{1}{20}&s=1$……….(III) On adding, 2(P + Q + R)'s 1 day's work $latex = \frac{1}{12}+\frac{1}{15}+\frac{1}{20} = \frac{5+4+3}{60} = \frac{1}{5}&s=1$ ∴ (P + Q + R)'s 1 day's work $latex = \frac{1}{5\times 2} = \frac{1}{10}&s=1$……….(IV) ∴ P's 1 day's work $latex = \frac{1}{10}-\frac{1}{15} = \frac{3-2}{20} = \frac{1}{30}&s=1$ ∴ P alone will complete the work in 30 days. Hence option [C] is correct answer.