BHEL commissions 40 MW hydropower plant in West Bengal

Public Sector Power equipment manufacturer Bharat Heavy Electricals Limited (BHEL) has commissioned the second 40 MW hydropower generating unit at the Teesta low dam hydroelectric project (HEP) stage IV in West Bengal.
The hydropower generating unit was successfully installed at the Teesta low dam HEP, a run-of-the-river greenfield project, located in Darjeeling district of the West Bengal.
Key facts

  • Teesta low dam HEP is being set up by National Hydroelectric Power Corporation (NHPC).
  • BHEL’s Bhopal, Jhansi, Rudrapur, Mumbai and Bengaluru facilities had supplied equipment for the project and execution of work was undertaken on site is being.
  • The estimated annual energy (power) generation from the project is around 720 million units.
  • It is expected to reduce green-house gas (GHGs) emissions and will help in achieving a low carbon development path for the state as well as the nation.

So far, BHEL has commissioned nearly 400 hydro generating sets of various ratings with a cumulative capacity of around 20,000 MW in the country.


Month: 

Leave a Reply