Analysing the problems of Power Discoms of India – GKToday

Analysing the problems of Power Discoms of India

Most of us get electricity in our houses and offices via the power distribution companies run by central and state governments. In India, the share of private sector in power generation has risen substantially over the past few years, but state electricity boards continue to own nearly 95% of the distribution network. Thus, the entire value chain of the power sector in India is dominated by the state owned companies.

These State Electricity Boards or SEBs are in existence for last 5 decades. Over the period of time, they have become unviable and unprofitable due to heavy accumulated losses and liabilities.

The T&D Losses and AT&C Losses

Inefficient planning, lack of investments, inadequate maintenance, low plant load factor, high transmission and distribution losses, erratic supply to consumers and other issues resulted in pathetic services and perennial financial losses. India’s power distribution segment is plagued by two types of losses:-

Here we should note that while the T&D Loss do not capture losses on account of non-realisation of payments. As the T&D loss was not able to capture all the losses in the net work, concept of Aggregate Technical and Commercial (AT&C) loss was introduced. AT&C loss captures technical as well as commercial losses in the network and is a true indicator of total losses in the system. AT&C Loss is the clearest measure of overall efficiency of the distribution business as it measures technical as well as commercial losses.

Thus, the reasons of the T&D and AT&C losses are:

The fraction of losses is very high. The T&D losses have been consistently on higher side, and reached to the level of 32.86% in the year 2000-01. Overall AT&C loss was 38.86% in 2001-02 At present (2012) the all-India T&D losses are 24.15 per cent. In 2009-10, the average AT&C loss for utilities selling directly to consumers stood at 27.2%.

Further, one more issue with the power distribution companies is the mismatch between tariffs and cost of generating power.

Poor Financial Conditions of SEBs

ARDRP Programme

The Government launched the Accelerated Power Development & Reform Programme (APDRP) was launched in 2001, for the strengthening of Transmission and Distribution network and reduction in AT&C losses. The scheme was launched to bring the AT&C losses below 15% in five years in urban and in high-density areas.

The scheme hardly met with any success. According to the Government claims, the scheme led to reduction in the overall AT&C loss from 38.86% in 2001-02 to 34.54% in 2005-06.Later, the government restructured the ARDRP programme. The Restructured APDRP (R-APDRP) was launched in 2008 as a central sector scheme for XI plan.

R-ARDRP Programme

The major problem of the previous APDRP was the inability to use the grants and failure to upgrade the system. The rechristened R-APDRP was launched with the intention to plug these loopholes and revamp the power scenario, by earmarking strict guidelines. This programme comprise of two main parts-Part-A & Part-B

To get assistance under the scheme, the states required to constitute the State Electricity Regulatory Commission and achieve the target of AT&C loss reduction at 3% per year for utilities that have AT&C loss above 30% and 1.5% for utilities having AT&C loss below 30%. The states were also required to commit a time frame for introduction of measures for better accountability at all levels in the project area. The monitoring was to be done by independent agency of Ministry of Power. Power Finance Corporation was designated by MoP as the nodal agency for operationalising the scheme.

The above scheme was launched with a lot of fanfare and optimism, but it could live up to the hype and euphoria. The first thing was that the project moved at snail’s pace. The SERCs were floated, IT companies joined the bandwagon, bids, tendering and re-tendering were all around. Pilot towns were announced. A new crop of IT consultants, GIS Consultants and Billing Consultants came up. When the dust sat down, we find that the AT&C losses were still high. The objective was to reduce the AT&C (aggregate technical and commercial) losses from the current level of over 30 per cent to less than 15 per cent over next five years, by automating and integrating IT. This Herculean task remains undone even today. Then, the NTPC and PGCIL were entrusted with the task of imparting consultancy to the aspiring DISCOMS. Both the organization were novice in the field of distribution of electricity, having no exposure to the complexity of distribution network and working of distribution units with no knowledge of constrains and problems of Discoms. APDRP could not achieve the desired goals within the stipulated time.

V.K. Shunglu Committee

In the backdrop of mounting losses in the power distribution segment, the Union Government approved a high level panel on Financial Position of Distribution Utilities to look into the financial problems of the SEBs/distribution utilities and to identify potential corrective steps, particularly in relation to their accounting practices. The panel was appointed in July 2010 and is headed by former comptroller and auditor general V.K. Shunglu. The committee submitted its report to the government in December last year.

The V.K. Shunglu committee’s terms of reference were as follows:

This committee restricted its analysis to distribution utilities for, poor operational efficiencies of these utilities end up affecting performance of generation and transmission utilities. It analysed the SEBs of 15 states that account for 91% of total power consumed in the country. It came up with the following recommendations & observations:

The SPV Model was not accepted because there was no response from RBI on the matter.

BK Chaturvedi Panel

Planning Commission had also set up a sub-committee headed by B K Chaturvedi to help restore the financial health of the utilities.

Recent Debt Restructuring Package

Under this plan, 50 per cent of the short-term outstanding liabilities of this distribution companies (Discoms) would be taken over by state governments. The debt will be first converted into bonds to be issued by discoms to participating lenders, duly backed by the state government’s guarantee. Balance 50 per cent loans would be restructured by providing moratorium on principle and best possible terms for repayments.

The package provided immediate relief to the Discoms. We should note that in 2001-02 also, the Centre had to provide a special financial package to save the state power sector from collapse when some of the state electricity boards defaulted on payment to central generators like NTPC and NHPC for power purchased from them. But the states did not learnt from that experience and continue to drag their feet.

Is it time to celebrate?

No. It is not. There are some of the major issues facing the power sector, yet to be resolved. Power producers are still grappling with coal shortage and land, environment clearance. Many companies are mired in legal tangles after having signed power purchase agreements at rates that are of bygone era. However, we have to see whether the state electricity boards learn to be disciplined this time in raising tariffs and curbing transmission and distribution losses. Union Government had also announced recently that it would bring a model State Electricity Distribution Responsibility Bill within a year to hold state discoms accountable for implementing power reforms under the newly-approved debt recast financial package approved by the States. States would have to enact the legislation within 12 months from the date of circulation of model legislation to mandate compliance of the provisions of the financial restructuring package.

Exit mobile version